Question

One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?

Options

  • AReduction in program quality
  • BDegradation of program communications
  • CReduction in program risk
  • DSlow down in program implementation