PSPO-II · Question #18
If burndown charts are used to visualize progress, what do they track? (Choose the best answer)
The correct answer is A. Work remaining across time. A burndown chart is a graphical tool that shows the amount of work remaining versus time. It is often used to track the progress of a Sprint or a release. The work remaining is usually measured in terms of effort, such as hours or story points, and it is plotted on the vertical…
Question
If burndown charts are used to visualize progress, what do they track? (Choose the best answer)
Options
- AWork remaining across time.
- BAccumulated cost.
- CAccumulated business value delivered to the customer.
- DIndividual worker productivity.
How the community answered
(48 responses)- A92% (44)
- B4% (2)
- C2% (1)
- D2% (1)
Explanation
A burndown chart is a graphical tool that shows the amount of work remaining versus time. It is often used to track the progress of a Sprint or a release. The work remaining is usually measured in terms of effort, such as hours or story points, and it is plotted on the vertical axis. The time is measured in terms of days or weeks, and it is plotted on the horizontal axis. The burndown chart starts with the total amount of work at the beginning of the Sprint or release, and it ideally ends with zero work at the end. The slope of the burndown chart indicates the rate of progress, or the velocity, of the Scrum Team.