The correct answer is A. Learn why the Development Team wants this, coach the team on why the Daily Scrum is. The Scrum Master is responsible for promoting and supporting Scrum as defined in the Scrum Scrum Masters do this by helping everyone understand Scrum theory, practices, rules, and

Question

The Development Team has suggested to move the Daily Scrum to every other day instead of every day. What is the most appropriate action for the Scrum Master to take?

Options

  • ALearn why the Development Team wants this, coach the team on why the Daily Scrum is
  • BSupport the self-organizing team's decision.
  • CHave the Development Team members vote on which days the Daily Scrum should occur.

Explanation

The Scrum Master is responsible for promoting and supporting Scrum as defined in the Scrum Scrum Masters do this by helping everyone understand Scrum theory, practices, rules, and