Question
A new Developer joins the Development Team taking the total number to 10 people. As a Scrum Master, What should you do?
Options
- ADo nothing, the Development Team must fix its own issues
- BRaise the increased team size as a potential impediment and help the Development Team decide
- CInstruct the Development Team to split into 2 teams, they should decide the appropriate sizes
- DInstruct the Development Team to split into 2 teams with 5 Developers in each