PSM-I · Question #98

What is the purpose of a Sprint Review?

The correct answer is B. To inspect the product increment with the stakeholders and collect feedback on next steps. The Sprint Review is an inspect-and-adapt event focused on the product. The Scrum Team presents the completed Increment to invited stakeholders, demonstrates working functionality, collects feedback, and collaborates on what should be tackled next - the output is a revised…

Submitted by naveen.iyer· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

What is the purpose of a Sprint Review?

Options

  • ATo take time to judge the validity of the project.
  • BTo inspect the product increment with the stakeholders and collect feedback on next steps.
  • CTo review the Scrum Team's activities and processes during the Sprint.
  • DTo build team sprint.

How the community answered

(21 responses)
  • B
    90% (19)
  • C
    5% (1)
  • D
    5% (1)

Explanation

The Sprint Review is an inspect-and-adapt event focused on the product. The Scrum Team presents the completed Increment to invited stakeholders, demonstrates working functionality, collects feedback, and collaborates on what should be tackled next - the output is a revised Product Backlog. Option A ('judge the validity of the project') mischaracterizes it as a go/no-go decision gate, which is not Scrum's intent. Option C describes the Sprint Retrospective, which focuses on the team's own processes and interactions, not the product. Option D is too vague to be meaningful.

Topics

#Sprint Review#Scrum Events#Product Increment#Stakeholder Feedback