The correct answer is C: What can be done and how to do it.. Sprint Planning covers two core topics: (1) What can be done — the team selects Product Backlog items they forecast they can complete, resulting in the Sprint Goal and selected backlog items; and (2) How to do it — the team designs the plan and decomposes the work into tasks
Question
Which answer best describes the topics covered in Sprint Planning?
Options
- AWhat to do and who will do it.
- BHow conditions have changed and how the Product Backlog should evolve.
- CWhat can be done and how to do it.
- DWhat went wrong in the last Sprint and what to do differently this Sprint.
- EWho is on the team and what team member roles will be.
Explanation
Sprint Planning covers two core topics: (1) What can be done — the team selects Product Backlog items they forecast they can complete, resulting in the Sprint Goal and selected backlog items; and (2) How to do it — the team designs the plan and decomposes the work into tasks to create the Sprint Backlog. Option A is misleading because Scrum does not assign work to individuals — the team self-organizes. Option B (how conditions have changed) relates to ongoing Product Backlog refinement. Option D (what went wrong) is the focus of the Sprint Retrospective. Option E (team roles) is an organizational concern, not Sprint Planning.