PSM-I · Question #96

PSM-I Question #96: Real Exam Question with Answer & Explanation

The correct answer is C: What can be done and how to do it.. Sprint Planning covers two core topics: (1) What can be done — the team selects Product Backlog items they forecast they can complete, resulting in the Sprint Goal and selected backlog items; and (2) How to do it — the team designs the plan and decomposes the work into tasks

Submitted by manish99· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Which answer best describes the topics covered in Sprint Planning?

Options

  • AWhat to do and who will do it.
  • BHow conditions have changed and how the Product Backlog should evolve.
  • CWhat can be done and how to do it.
  • DWhat went wrong in the last Sprint and what to do differently this Sprint.
  • EWho is on the team and what team member roles will be.

Explanation

Sprint Planning covers two core topics: (1) What can be done — the team selects Product Backlog items they forecast they can complete, resulting in the Sprint Goal and selected backlog items; and (2) How to do it — the team designs the plan and decomposes the work into tasks to create the Sprint Backlog. Option A is misleading because Scrum does not assign work to individuals — the team self-organizes. Option B (how conditions have changed) relates to ongoing Product Backlog refinement. Option D (what went wrong) is the focus of the Sprint Retrospective. Option E (team roles) is an organizational concern, not Sprint Planning.