PSM-I · Question #96
Which answer best describes the topics covered in Sprint Planning?
The correct answer is C. What can be done and how to do it. Sprint Planning covers two core topics: (1) What can be done - the team selects Product Backlog items they forecast they can complete, resulting in the Sprint Goal and selected backlog items; and (2) How to do it - the team designs the plan and decomposes the work into tasks to…
Question
Which answer best describes the topics covered in Sprint Planning?
Options
- AWhat to do and who will do it.
- BHow conditions have changed and how the Product Backlog should evolve.
- CWhat can be done and how to do it.
- DWhat went wrong in the last Sprint and what to do differently this Sprint.
- EWho is on the team and what team member roles will be.
How the community answered
(27 responses)- A4% (1)
- C93% (25)
- E4% (1)
Explanation
Sprint Planning covers two core topics: (1) What can be done - the team selects Product Backlog items they forecast they can complete, resulting in the Sprint Goal and selected backlog items; and (2) How to do it - the team designs the plan and decomposes the work into tasks to create the Sprint Backlog. Option A is misleading because Scrum does not assign work to individuals - the team self-organizes. Option B (how conditions have changed) relates to ongoing Product Backlog refinement. Option D (what went wrong) is the focus of the Sprint Retrospective. Option E (team roles) is an organizational concern, not Sprint Planning.
Topics
Community Discussion
No community discussion yet for this question.