PSM-I · Question #89
PSM-I Question #89: Real Exam Question with Answer & Explanation
The correct answer is B: The Sprint Goal. The Sprint Goal is the single, overarching objective agreed upon during Sprint Planning. It gives the Development Team a clear target and the flexibility to determine how best to achieve it. If something unexpected arises, the team can negotiate scope with the Product Owner while
Question
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
Options
- AThe Sprint Backlog.
- BThe Sprint Goal
- CThe release plan.
- DSprint Review minutes.
Explanation
The Sprint Goal is the single, overarching objective agreed upon during Sprint Planning. It gives the Development Team a clear target and the flexibility to determine how best to achieve it. If something unexpected arises, the team can negotiate scope with the Product Owner while keeping the Sprint Goal intact. The Sprint Backlog (A) lists specific tasks and items but does not articulate the strategic direction. The release plan (C) is broader than a single Sprint. Sprint Review minutes (D) are artifacts from a past Sprint, not a current-Sprint guide.
Topics
Community Discussion
No community discussion yet for this question.