PSM-I · Question #82

PSM-I Question #82: Real Exam Question with Answer & Explanation

The correct answer is D: The Product Owner. The Product Owner is responsible for maximizing the value of the product and monitoring progress toward high-level goals (i.e., the Product Goal). This includes tracking total work remaining versus the goal, managing the Product Backlog, and communicating progress to stakeholders

Submitted by layla.eg· Apr 18, 2026Managing Products with Agility

Question

Who is responsible for monitoring progress toward high-level goals?

Options

  • AThe Scrum Master and The Development Team
  • BThe Scrum Master
  • CThe Product Owner and The Development Team
  • DThe Product Owner
  • EThe Development Team
  • FThe Scrum Team

Explanation

The Product Owner is responsible for maximizing the value of the product and monitoring progress toward high-level goals (i.e., the Product Goal). This includes tracking total work remaining versus the goal, managing the Product Backlog, and communicating progress to stakeholders. The Development Team monitors Sprint-level progress, but high-level goal tracking belongs to the Product Owner.

Topics

#Product Owner responsibilities#Product Goal#Progress monitoring#Accountability