PSM-I · Question #70

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should

Sign in or unlock PSM-I to reveal the answer and full explanation for question #70. The question stem and answer options stay visible for context.

Submitted by olafpl· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)

Options

  • AThere should be six Product Owners, one for each Scrum Team.
  • BThere should be six Product Owners, reporting to a chief Product Owner.
  • CThe product has one Product Backlog.
  • DEach Scrum Team should have a separate Product Backlog.
  • EThere should be only one Product Owner.

Unlock PSM-I to see the answer

You've previewed enough free PSM-I questions. Unlock PSM-I for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Product Owner#Product Backlog#Scrum Teams#Scaling Scrum