The correct answer is C: The product has one Product Backlog.. The product has one Product Backlog, as it is a single source of requirements for any changes to be made to the product. There should be only one Product Owner, who is accountable for maximizing the value of the product and the work of the Development Team. Having multiple Produc
Question
You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)
Options
- AThere should be six Product Owners, one for each Scrum Team.
- BThere should be six Product Owners, reporting to a chief Product Owner.
- CThe product has one Product Backlog.
- DEach Scrum Team should have a separate Product Backlog.
- EThere should be only one Product Owner.
Explanation
The product has one Product Backlog, as it is a single source of requirements for any changes to be made to the product. There should be only one Product Owner, who is accountable for maximizing the value of the product and the work of the Development Team. Having multiple Product Owners or Product Backlogs would create confusion, inconsistency, and waste.