PSM-I · Question #66
The Product Backlog is ordered by:
The correct answer is A. The Product Owner with the most valuable items placed at the top. The Product Owner is solely responsible for ordering the Product Backlog, and the primary criterion is value - the most valuable items are placed at the top so the Development Team works on the highest-priority items first. The Product Owner may consider factors like risk…
Question
The Product Backlog is ordered by:
Options
- AThe Product Owner with the most valuable items placed at the top.
- BRisk, where safer items are at the top, and riskier items are at the bottom.
- CItems are randomly arranged.
- DSize, where small items ale at the top and large items are at the bottom.
How the community answered
(30 responses)- A90% (27)
- B3% (1)
- C7% (2)
Explanation
The Product Owner is solely responsible for ordering the Product Backlog, and the primary criterion is value - the most valuable items are placed at the top so the Development Team works on the highest-priority items first. The Product Owner may consider factors like risk, dependencies, and size when ordering, but these are inputs to a value-based decision, not the default ordering method. Options B, C, and D describe specific ordering strategies that might be used occasionally but are not how the Product Backlog is defined to be ordered in Scrum.