PSM-I · Question #61
PSM-I Question #61: Real Exam Question with Answer & Explanation
The correct answer is D: It is the Development Team's plan for the Sprint.. The Sprint Backlog is the Development Team's plan for achieving the Sprint Goal. It consists of the selected Product Backlog items plus a plan for delivering them. It is NOT an exhaustive task list for all work, items do not have designated owners (anyone on the team can pick up
Question
Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?
Options
- AIt is a complete list of all work to be done in a Sprint.
- BEvery item has a designated owner.
- CEach task is estimated in hours.
- DIt is the Development Team's plan for the Sprint.
- EIt is ordered by the Product Owner.
Explanation
The Sprint Backlog is the Development Team's plan for achieving the Sprint Goal. It consists of the selected Product Backlog items plus a plan for delivering them. It is NOT an exhaustive task list for all work, items do not have designated owners (anyone on the team can pick up work), tasks are not required to be estimated in hours, and the Product Owner does not order it — the Development Team owns and manages it.