PSM-I · Question #56
At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of "Done". What two things should happen with the undone Product Backlog item? (Choose two.)
Sign in or unlock PSM-I to reveal the answer and full explanation for question #56. The question stem and answer options stay visible for context.
Submitted by diego_uy· Apr 18, 2026Understanding and Applying the Scrum Framework
Question
At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of "Done". What two things should happen with the undone Product Backlog item? (Choose two.)
Options
- AIf the stakeholders agree, the Product Owner can accept it and release it to the users.
- BPut it on the Product Backlog for the Product Owner to decide what to do with it.
- CReview the item, add the "Done" part of the estimate to the velocity and create a Story for the
- DDo not include the item in the Increment this Sprint.
Unlock PSM-I to see the answer
You've previewed enough free PSM-I questions. Unlock PSM-I for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Definition of Done#Increment#Product Backlog#Sprint End