Question

Every Development Team should have:

Options

  • AAt least one representative from each major software engineering discipline (like QA, Dev, UX).
  • BThe competencies and skills needed to deliver a Done Increment in a Sprint.
  • COne Lead Developer and no more than 8 other members.