PSM-I · Question #279
Which statement best describes the Sprint Backlog as the output ot the Sprint Planning? (Choose the best answer)
The correct answer is D. It is the Developers plan for the Sprint. According to the Scrum Guide, the Sprint Backlog is the Developers' plan for the Sprint, as it contains all the Product Backlog items selected for the Sprint and a plan for delivering them. The other options are not valid descriptions of the Sprint Backlog, as they are either…
Question
Which statement best describes the Sprint Backlog as the output ot the Sprint Planning? (Choose the best answer)
Options
- AEvery item nas a designated owner.
- BIt is ordered by the Product Owner.
- CEach task is estimated in hours.
- DIt is the Developers plan for the Sprint
- EIt is a complete list of all work to be done in a Sprint.
How the community answered
(36 responses)- A3% (1)
- B6% (2)
- C3% (1)
- D89% (32)
Explanation
According to the Scrum Guide, the Sprint Backlog is the Developers' plan for the Sprint, as it contains all the Product Backlog items selected for the Sprint and a plan for delivering them. The other options are not valid descriptions of the Sprint Backlog, as they are either incorrect (such as having a designated owner, being ordered by the Product Owner, or being a complete list of all work) or unnecessary (such as estimating each task in hours).
Topics
Community Discussion
No community discussion yet for this question.