PSM-I · Question #256

PSM-I Question #256: Real Exam Question with Answer & Explanation

The correct answer is B: False. According to the Scrum Guide, multiple Scrum Teams working on the same product do not have to have the same Sprint start date. They may start their Sprints at different times, as long as they synchronize their work and integrate their Increments at least by the end of each Sprint

Submitted by suresh_in· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

True or False: Multiple scrum Teams working on the same product must have the same Sprint start date.

Options

  • ATrue
  • BFalse

Explanation

According to the Scrum Guide, multiple Scrum Teams working on the same product do not have to have the same Sprint start date. They may start their Sprints at different times, as long as they synchronize their work and integrate their Increments at least by the end of each Sprint. The other option is not valid, as it implies that having the same Sprint start date is mandatory for multiple Scrum Teams.

Topics

#Multiple Teams#Scaling Scrum#Sprint Synchronization#Scrum Team Autonomy