PSM-I · Question #237
Who has the final decision about the order of items in the Product Backlog? (Choose the best answer.)
The correct answer is B. The Product Owner. According to the Scrum Guide, the Product Owner has the final decision about the order of items in the Product Backlog, as he or she is responsible for maximizing the value of the product and the work of the Development Team. The other roles do not have this authority, although…
Question
Who has the final decision about the order of items in the Product Backlog? (Choose the best answer.)
Options
- AThe Stakeholders.
- BThe Product Owner.
- CThe Scrum Team.
- DThe Scrum Master.
- EThe Developers.
How the community answered
(42 responses)- A7% (3)
- B88% (37)
- C2% (1)
- D2% (1)
Explanation
According to the Scrum Guide, the Product Owner has the final decision about the order of items in the Product Backlog, as he or she is responsible for maximizing the value of the product and the work of the Development Team. The other roles do not have this authority, although they may provide input and suggestions to the Product Owner.
Topics
Community Discussion
No community discussion yet for this question.