PSM-I · Question #235
PSM-I Question #235: Real Exam Question with Answer & Explanation
The correct answer is C: Team relations. According to the Scrum Guide, the Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. The topics that are appropriate for discussion are those that relate to how the team does its wor
Question
Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)
Options
- AArranging the Sprint Backlog for the next Sprint.
- BThe value of work currently represented in the Product Backlog.
- CTeam relations
- DDefinition of Done.
- EHow the Scrum Team does its work.
Explanation
According to the Scrum Guide, the Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint. The topics that are appropriate for discussion are those that relate to how the team does its work, such as team relations, Definition of Done, and processes, tools, communication, collaboration, quality, etc. The other options are not appropriate topics for discussion in a Sprint Retrospective, as they belong to other Scrum events (such as arranging the Sprint Backlog for the next Sprint in the Sprint Planning or evaluating the value of work in the Product Backlog in the Sprint Review).