Which topics should be discussed in the Sprint Review? (Choose the best answer.)

The correct answer is C. The product Increment. The Sprint Review is an inspection of the product Increment and an opportunity to adapt the Product Backlog based on stakeholder feedback. It is NOT about the Scrum process (A) - that belongs in the Sprint Retrospective - nor about internal coding or engineering practices (B)…

Submitted by mike_84· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Which topics should be discussed in the Sprint Review? (Choose the best answer.)

Options

  • AThe Scrum process, and how it was used during the Sprint.
  • BCoding and engineering practices.
  • CThe product Increment.
  • DAll of the above.

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    88% (23)

Explanation

The Sprint Review is an inspection of the product Increment and an opportunity to adapt the Product Backlog based on stakeholder feedback. It is NOT about the Scrum process (A) - that belongs in the Sprint Retrospective - nor about internal coding or engineering practices (B). Because A and B do not belong in a Sprint Review, 'All of the above' (D) is also incorrect.

Topics

#Sprint Review#Scrum Events#Product Increment#Stakeholder Collaboration