PSM-I · Question #216
When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
The correct answer is C. The Product Owner and the Development Team. When a Development Team determines that it will not be able to finish the complete forecast, both the Product Owner and the Development Team have to be present when reviewing and adjusting the Sprint work selected, as stated in: "If there is not enough work remaining for all…
Question
When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
Options
- AThe Development Team.
- BThe Product Owner and all stakeholders.
- CThe Product Owner and the Development Team.
- DThe Scrum Master, project manager and Development Team.
How the community answered
(33 responses)- A3% (1)
- B15% (5)
- C70% (23)
- D12% (4)
Explanation
When a Development Team determines that it will not be able to finish the complete forecast, both the Product Owner and the Development Team have to be present when reviewing and adjusting the Sprint work selected, as stated in: "If there is not enough work remaining for all members of a Development Team then they can renegotiate scope with their Product Owner. If there is too much work remaining then they can also renegotiate scope with their Product
Topics
Community Discussion
No community discussion yet for this question.