nerdexam
Scrum

PSM-I · Question #214

When many Development Teams are working on a single product, what best describes the definition of "Done"? (Choose the best answer.)

The correct answer is D. All Development Teams must have a definition of "Done" that makes their combined work. When many Development Teams are working on a single product, the definition of "Done" must be shared by all Development Teams and make their combined work potentially releasable, as stated in: "When multiple teams work together on one product they must mutually define and…

Submitted by andreas_gr· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

When many Development Teams are working on a single product, what best describes the definition of "Done"? (Choose the best answer.)

Options

  • AEach Development Team defines and uses its own. The differences are discussed and reconciled
  • BIt depends.
  • CEach Development Team uses its own but must make their definition clear to all other teams so
  • DAll Development Teams must have a definition of "Done" that makes their combined work

How the community answered

(56 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    2% (1)
  • D
    93% (52)

Explanation

When many Development Teams are working on a single product, the definition of "Done" must be shared by all Development Teams and make their combined work potentially releasable, as stated in: "When multiple teams work together on one product they must mutually define and comply with the same Definition of Done. This makes sure all Increments adhere to a consistent

Topics

#Definition of Done#Multiple Scrum Teams#Product Increment#Scrum Guide

Community Discussion

No community discussion yet for this question.

Full PSM-I Practice