The correct answer is D: All Development Teams must have a definition of "Done" that makes their combined work. When many Development Teams are working on a single product, the definition of "Done" must be shared by all Development Teams and make their combined work potentially releasable, as stated in: "When multiple teams work together on one product they must mutually define and comply
Question
When many Development Teams are working on a single product, what best describes the definition of "Done"? (Choose the best answer.)
Options
- AEach Development Team defines and uses its own. The differences are discussed and reconciled
- BIt depends.
- CEach Development Team uses its own but must make their definition clear to all other teams so
- DAll Development Teams must have a definition of "Done" that makes their combined work
Explanation
When many Development Teams are working on a single product, the definition of "Done" must be shared by all Development Teams and make their combined work potentially releasable, as stated in: "When multiple teams work together on one product they must mutually define and comply with the same Definition of Done. This makes sure all Increments adhere to a consistent