The correct answer is A: Development Team has all the skills to create a potentially releasable increment by the end of. According to the Scrum Guide, a Development Team is cross-functional if it has all the skills to create a potentially releasable Increment by the end of every Sprint. The other options are not indicators of cross-functionality, as they are either specific practices (such as pair

Submitted by skyler.x· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

How do you know that a Development Team is cross-functional?

Options

  • ADevelopment Team has all the skills to create a potentially releasable increment by the end of
  • BA few of the Development Team members pair program and do Test Driven Development.
  • CThere are no conflicts within the Development Team.
  • DEvery member of the Development Team is able to perform every task.

Explanation

According to the Scrum Guide, a Development Team is cross-functional if it has all the skills to create a potentially releasable Increment by the end of every Sprint. The other options are not indicators of cross-functionality, as they are either specific practices (such as pair programming or test driven development) or irrelevant factors (such as conflicts within the team or ability to perform every task).

Topics

#Cross-functional Team#Development Team#Scrum Team Characteristics#Product Increment

Community Discussion

No community discussion yet for this question.

Full PSM-I PracticeBrowse All PSM-I Questions