PSM-I · Question #202
PSM-I Question #202: Real Exam Question with Answer & Explanation
The correct answer is A: The Development Team.. The Development Team is responsible for tracking remaining work in the Sprint Backlog. They update it throughout the Sprint — typically each day at the Daily Scrum — to reflect progress and forecast whether the Sprint Goal will be met. This self-management is a core Scrum pri
Question
Who is responsible for tracking the remaining work of the Sprint?
Options
- AThe Development Team.
- BThe Scrum Master.
- CThe Project Manager.
- DThe Development Team is consultation with the Product Owner.
- EThe Product Owner.
Explanation
The Development Team is responsible for tracking remaining work in the Sprint Backlog. They update it throughout the Sprint — typically each day at the Daily Scrum — to reflect progress and forecast whether the Sprint Goal will be met. This self-management is a core Scrum principle. The Scrum Master (B) facilitates and removes impediments but does not manage the team's work. The Project Manager (C) is not a Scrum role. The Product Owner (E) manages the Product Backlog, not the Sprint Backlog.
Topics
Community Discussion
No community discussion yet for this question.