PSM-I · Question #18

PSM-I Question #18: Real Exam Question with Answer & Explanation

Sign in or unlock PSM-I to reveal the answer and full explanation for question #18. The question stem and answer options stay visible for context.

Submitted by miguelv· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Which are properties of the Daily Scrum? (Choose two.)

Options

  • AIt is facilitated by the team lead.
  • BIt is held first thing in the morning.
  • CIt is fifteen minutes or less in duration.
  • DIt is free from and designed to promote conversation.
  • EIt consists of the Scrum Master asking the Team members the three questions.
  • FIts location and time remain constant.

Unlock PSM-I to see the answer