During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
Options
- AWhen the Product Owner identifies new work.
- BAs soon as possible after they are identified.
- CWhen the Scrum Master has time to enter them.
- DDuring the Daily Scrum after the Development Team approves them.