Multiple Scrum Teams working on the same project must have the same Sprint start date.
The correct answer is B. False. False. The Scrum Guide does not require multiple Scrum Teams on the same product to share the same Sprint start date. In practice, synchronized Sprints are often recommended to simplify coordination (e.g., shared Sprint Reviews, integrated increments), but it is not a rule…
Question
Multiple Scrum Teams working on the same project must have the same Sprint start date.
Options
- ATrue
- BFalse
How the community answered
(30 responses)- A10% (3)
- B90% (27)
Explanation
False. The Scrum Guide does not require multiple Scrum Teams on the same product to share the same Sprint start date. In practice, synchronized Sprints are often recommended to simplify coordination (e.g., shared Sprint Reviews, integrated increments), but it is not a rule. Each team may run its own Sprint cadence. What is required is that all teams work toward the same Product Goal and integrate their work into a single potentially releasable Increment.
Topics
Community Discussion
No community discussion yet for this question.