PSM-I · Question #133
Who should make sure everyone on the Development Team does his or her tasks for the Sprint?
The correct answer is D. The Development Team. According to the Scrum Guide, the Developers are self-organizing and decide how to turn Product Backlog items into an Increment of value. No one tells them how to do their work. The Developers are accountable for creating a plan for the Sprint, the Sprint Backlog. The other…
Question
Who should make sure everyone on the Development Team does his or her tasks for the Sprint?
Options
- AThe Project Manager.
- BThe Product Owner.
- CThe Scrum Master.
- DThe Development Team.
- EAll of the above.
How the community answered
(57 responses)- A4% (2)
- C2% (1)
- D95% (54)
Explanation
According to the Scrum Guide, the Developers are self-organizing and decide how to turn Product Backlog items into an Increment of value. No one tells them how to do their work. The Developers are accountable for creating a plan for the Sprint, the Sprint Backlog. The other roles are not responsible for making sure everyone on the Development Team does their tasks for the