Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
The correct answer is D. Answer questions from the Development Team about items in the current Sprint. E. Work with the stakeholders. The correct answers are D and E, because these are two activities that a Product Owner can engage in during a Sprint. The Scrum Guide states that "the Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team." Therefore…
Question
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
Options
- ARun the Daily Scrum.
- BPrioritize the Development Team's work on the Sprint Backlog.
- CUpdate the Sprint burndown chart.
- DAnswer questions from the Development Team about items in the current Sprint.
- EWork with the stakeholders.
How the community answered
(19 responses)- B5% (1)
- D95% (18)
Explanation
The correct answers are D and E, because these are two activities that a Product Owner can engage in during a Sprint. The Scrum Guide states that "the Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team." Therefore, the Product Owner can answer questions from the Development Team about items in the current Sprint, and work with the stakeholders to understand their needs and expectations.