PSM-I · Question #123

PSM-I Question #123: Real Exam Question with Answer & Explanation

The correct answer is C: Frequently, but it should not get in the way of the work. The Scrum Guide states that inspection should happen frequently, but not so frequently that it gets in the way of the work. Inspection is one of Scrum's three pillars (transparency, inspection, adaptation), but excessive inspection creates overhead and disruption. Choice A (only

Submitted by satoshi_tk· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

How frequently should scrum users inspect Scrum artifacts and progress toward a Sprint Goal?

Options

  • AAt the Sprint Review
  • BAfter the Daily Scrum
  • CFrequently, but it should not get in the way of the work
  • DAs frequently as possible

Explanation

The Scrum Guide states that inspection should happen frequently, but not so frequently that it gets in the way of the work. Inspection is one of Scrum's three pillars (transparency, inspection, adaptation), but excessive inspection creates overhead and disruption. Choice A (only at Sprint Review) is too infrequent. Choice D ('as frequently as possible') sounds correct but contradicts the Scrum Guide's explicit caveat about not impeding the work. The correct balance is frequent but pragmatic inspection.

Topics

#Inspection#Scrum Pillars#Scrum Artifacts#Sprint Goal Progress

Community Discussion

No community discussion yet for this question.