PRINCE2-AGILE-FOUNDATION · Question #71

Which statement about the `be on time and hit deadlines' target is CORRECT?

The correct answer is C. It helps with planning dependencies within a project. You've hit your limit · resets 5am (America/New_York)

Agile Ways of Working

Question

Which statement about the `be on time and hit deadlines' target is CORRECT?

Options

  • AIt allows change to be handled dynamically
  • BIt is achieved by keeping the delivery teams stable
  • CIt helps with planning dependencies within a project
  • DIt ensures that the level of quality is protected

How the community answered

(22 responses)
  • A
    9% (2)
  • B
    5% (1)
  • C
    86% (19)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#PRINCE2 Agile targets#deadlines#planning dependencies