PRINCE2-AGILE-FOUNDATION · Question #65

Which statement about an epic is CORRECT?

The correct answer is A. It can be broken down into user stories. You've hit your limit · resets 5am (America/New_York)

Agile Ways of Working

Question

Which statement about an epic is CORRECT?

Options

  • AIt can be broken down into user stories
  • BIts purpose is to document technical requirements
  • CIt should appear at the top of a product backlog
  • DIt contains sufficient granularity to allow work to start

How the community answered

(30 responses)
  • A
    87% (26)
  • B
    3% (1)
  • C
    3% (1)
  • D
    7% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#epics#user stories#product backlog#requirements decomposition