Which TWO statements about the supplier subject matter expert are CORRECT? 1. They provide a wider picture of the customer view. 2. They prioritize requirements at the detailed level. 3. They should…

The correct answer is C. 3 and 4. You've hit your limit · resets 5am (America/New_York)

PRINCE2 Agile Roles and Responsibilities

Question

Which TWO statements about the supplier subject matter expert are CORRECT? 1. They provide a wider picture of the customer view. 2. They prioritize requirements at the detailed level. 3. They should be focused on the customer. 4. They ensure that the work is compliant with project standards.

Options

  • A1 and 2
  • B2 and 3
  • C3 and 4
  • D1 and 4

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    86% (36)
  • D
    7% (3)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#supplier subject matter expert#PRINCE2 Agile roles#customer focus