Question

Which statement about the `initiating a project' process is CORRECT?

Options

  • AThe initiation stage plan should form part of the project plan
  • BThe impact of frequent releases on quality management should be assessed
  • CThe process should take more time than usual for disruptive projects
  • DThe project solution should be documented in detail in the project product description

Unlock PRINCE2-AGILE-FOUNDATION to see the answer