PRINCE2-AGILE-FOUNDATION · Question #61

Which statement about the waterfall methodology definition is CORRECT?

The correct answer is A. It prevents earlier phases of development being revisited. You've hit your limit · resets 5am (America/New_York)

Understanding Agile Concepts and Approaches

Question

Which statement about the waterfall methodology definition is CORRECT?

Options

  • AIt prevents earlier phases of development being revisited
  • BIt uses an iterative and incremental approach
  • CIt focuses on responding to changing requirements
  • DIt delivers products more frequently in shorter phases

How the community answered

(43 responses)
  • A
    93% (40)
  • C
    2% (1)
  • D
    5% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#waterfall methodology#sequential phases#SDLC models