Which statement about timeboxes is CORRECT?
The correct answer is C. A timebox can contain another timebox. You've hit your limit · resets 5am (America/New_York)
Understanding Agile Concepts and Approaches
Question
Which statement about timeboxes is CORRECT?
Options
- AFlow based working partitions work into timeboxes
- BA project cannot be referred to as a timebox
- CA timebox can contain another timebox
- DTimeboxes should be avoided in business as usual environments
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C86% (24)
- D4% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#timeboxes#agile planning#iterations