Which statement about timeboxes is CORRECT?

The correct answer is C. A timebox can contain another timebox. You've hit your limit · resets 5am (America/New_York)

Understanding Agile Concepts and Approaches

Question

Which statement about timeboxes is CORRECT?

Options

  • AFlow based working partitions work into timeboxes
  • BA project cannot be referred to as a timebox
  • CA timebox can contain another timebox
  • DTimeboxes should be avoided in business as usual environments

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    86% (24)
  • D
    4% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#timeboxes#agile planning#iterations