Which TWO project board responsibilities are specifically assigned to the senior user? 1. Demonstrating the achievement of benefits. 2. Specifying the needs of those impacted by the outputs. 3…

The correct answer is A. 1 and 2. You've hit your limit · resets 5am (America/New_York)

PRINCE2 Roles and Responsibilities

Question

Which TWO project board responsibilities are specifically assigned to the senior user? 1. Demonstrating the achievement of benefits. 2. Specifying the needs of those impacted by the outputs. 3. Balancing business, user and supplier demands. 4. Ensuring that the project delivers value for money.

Options

  • A1 and 2
  • B2 and 3
  • C3 and 4
  • D1 and 4

How the community answered

(31 responses)
  • A
    90% (28)
  • B
    3% (1)
  • C
    3% (1)
  • D
    3% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#senior user#project board roles#benefits realization#stakeholder needs

Community Discussion

No community discussion yet for this question.

Full PRINCE2-AGILE-FOUNDATION Practice