PRINCE2
PRINCE2-AGILE-FOUNDATION · Question #174
Which statement about the 'directing a project' process is CORRECT?
The correct answer is A. The project board may pull reports from the information radiator. You've hit your limit · resets 5am (America/New_York)
PRINCE2 Processes
Question
Which statement about the ’directing a project' process is CORRECT?
Options
- AThe project board may pull reports from the information radiator
- BAs a minimum, the project board should receive oral reports from the project manager
- CThe project board should attend the delivery team's daily stand up meeting
- DThe project board should receive regular reports focusing on cost and time overruns
How the community answered
(61 responses)- A84% (51)
- B10% (6)
- C5% (3)
- D2% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#directing a project#project board#information radiator#reporting
Community Discussion
No community discussion yet for this question.