Which statement about the PRINCE2 Agile behaviour 'collaboration' is CORRECT?

The correct answer is C. It creates a shared ownership of goals. You've hit your limit · resets 5am (America/New_York)

PRINCE2 Agile Behaviours

Question

Which statement about the PRINCE2 Agile behaviour ‘collaboration' is CORRECT?

Options

  • AIt allows many small learnings to accumulate over time
  • BIt allows the delivery team to decide how best to get the job done
  • CIt creates a shared ownership of goals
  • DIt uses the most effective channel to communicate

How the community answered

(41 responses)
  • A
    2% (1)
  • B
    7% (3)
  • C
    88% (36)
  • D
    2% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#collaboration#PRINCE2 Agile behaviours#shared ownership#team