PRINCE2-AGILE-FOUNDATION · Question #3
In which process should the requirements for delivery of specialist products be agreed?
The correct answer is B. Managing product delivery. The Managing Product Delivery process includes agreeing on and controlling the requirements for the delivery of specialist products. This process ensures that team managers understand the scope and quality expectations before work begins and that delivery aligns with the…
Question
In which process should the requirements for delivery of specialist products be agreed?
Options
- AInitiating a project
- BManaging product delivery
- CStarting up a project
- DManaging a stage boundary
How the community answered
(29 responses)- A7% (2)
- B72% (21)
- C3% (1)
- D17% (5)
Explanation
The Managing Product Delivery process includes agreeing on and controlling the requirements for the delivery of specialist products. This process ensures that team managers understand the scope and quality expectations before work begins and that delivery aligns with the project plan. Initiating a project and starting up a project establish overall direction but do not handle detailed delivery requirements. Managing a stage boundary reviews progress and plans the next stage. This process maintains clarity and accountability for delivery within PRINCE2's framework, facilitating effective control over specialist products.
Topics
Community Discussion
No community discussion yet for this question.