PRINCE2-AGILE-FOUNDATION · Question #136

Which of the following statements about fixing and flexing tolerances is INCORRECT?

The correct answer is C. Zero tolerance on quality criteria that are desirable but not essential. You've hit your limit · resets 5am (America/New_York)

Tailoring PRINCE2 for Agile

Question

Which of the following statements about fixing and flexing tolerances is INCORRECT?

Options

  • AZero tolerance on extra time on all levels of plan
  • BZero tolerance on benefits defined as 搈inimum viability?in the business case
  • CZero tolerance on quality criteria that are desirable but not essential
  • DZero tolerance on products that are essential

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    6% (2)
  • C
    81% (25)
  • D
    3% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#tolerances#quality criteria#fixing and flexing#scope management