Which does NOT describe PRINCE2 Agile according to the eight guidance points?

The correct answer is C. A PRINCE2 Agile project that does not use Scrum cannot be considered agile. You've hit your limit · resets 5am (America/New_York)

PRINCE2 Agile Fundamentals

Question

Which does NOT describe PRINCE2 Agile according to the eight guidance points?

Options

  • APRINCE2 allows for any style of working including environments with high levels of uncertainty
  • BPRINCE2 Agile does not assume an IT context
  • CA PRINCE2 Agile project that does not use Scrum cannot be considered agile
  • DNothing about PRINCE2 should be removed from PRINCE2 Agile project

How the community answered

(42 responses)
  • A
    14% (6)
  • B
    7% (3)
  • C
    76% (32)
  • D
    2% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#guidance points#Scrum#agile frameworks#PRINCE2 Agile principles

Community Discussion

No community discussion yet for this question.

Full PRINCE2-AGILE-FOUNDATION Practice