PRINCE2
PRINCE2-AGILE-FOUNDATION · Question #135
Which does NOT describe PRINCE2 Agile according to the eight guidance points?
The correct answer is C. A PRINCE2 Agile project that does not use Scrum cannot be considered agile. You've hit your limit · resets 5am (America/New_York)
PRINCE2 Agile Fundamentals
Question
Which does NOT describe PRINCE2 Agile according to the eight guidance points?
Options
- APRINCE2 allows for any style of working including environments with high levels of uncertainty
- BPRINCE2 Agile does not assume an IT context
- CA PRINCE2 Agile project that does not use Scrum cannot be considered agile
- DNothing about PRINCE2 should be removed from PRINCE2 Agile project
How the community answered
(42 responses)- A14% (6)
- B7% (3)
- C76% (32)
- D2% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#guidance points#Scrum#agile frameworks#PRINCE2 Agile principles
Community Discussion