PRINCE2-AGILE-FOUNDATION · Question #124
Which statement explains the setting of the cost tolerance for a project in an agile context?
The correct answer is A. Cost tolerance is flexed. You've hit your limit · resets 5am (America/New_York)
Tailoring PRINCE2 for Agile
Question
Which statement explains the setting of the cost tolerance for a project in an agile context?
Options
- ACost tolerance is flexed
- BCost tolerance can be fixed or flexed
- CCost tolerance can be fixed and flexed
- DCost tolerance is fixed
How the community answered
(53 responses)- A87% (46)
- B8% (4)
- C2% (1)
- D4% (2)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#cost tolerance#fixing and flexing#tolerances#constraints