Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
The correct answer is A. To use empiricism, based on knowledge that comes from experience. You've hit your limit · resets 5am (America/New_York)
Lean and Agile Concepts
Question
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
Options
- ATo use empiricism, based on knowledge that comes from experience
- BTo build, measure, learn from your experiences
- CTo create a minimum viable product to manage uncertainty
- DTo fail fast, if you are going to fail
How the community answered
(28 responses)- A71% (20)
- B18% (5)
- C4% (1)
- D7% (2)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#Lean Startup#empiricism#MVP#fail fast