PR2F · Question #96

Which of the following is FALSE regarding the Change theme?

The correct answer is A. Change control should be used to prevent changes being made to baselined products. See the full explanation below for the reasoning.

Question

Which of the following is FALSE regarding the Change theme?

Options

  • AChange control should be used to prevent changes being made to baselined products
  • BIssues can affect the project's performance targets of time, cost, quality, scope, benefits and risk
  • CA pre-requisite of effective issue and change control would be an appropriate configuration
  • DWithout issue and change control being applied, a project will become unresponsive to its

How the community answered

(26 responses)
  • A
    85% (22)
  • B
    4% (1)
  • C
    4% (1)
  • D
    8% (2)