PR2F · Question #75
Which product would be updated with the planned quality management activities for the next stage of the project?
The correct answer is D. Quality Register. See the full explanation below for the reasoning.
Question
Which product would be updated with the planned quality management activities for the next stage of the project?
Options
- AQuality Management Strategy
- BIssue Register
- CProject Initiation Documentation
- DQuality Register
How the community answered
(62 responses)- A2% (1)
- B10% (6)
- C5% (3)
- D84% (52)