Once a product has been completed, from who would the Team Manager get approval for its completion?

The correct answer is B. The authority defined in the quality responsibilities section of the product's Product Description. See the full explanation below for the reasoning.

Question

Once a product has been completed, from who would the Team Manager get approval for its completion?

Options

  • AProject Manager
  • BThe authority defined in the quality responsibilities section of the product's Product Description
  • CQuality Assurance as part of their independent audits
  • DProject Support

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    78% (18)
  • C
    4% (1)
  • D
    9% (2)