PR2F · Question #7
Which is a responsibility of the Project Assurance role?
The correct answer is A. Inform the Project Manager about the status of the project's products. See the full explanation below for the reasoning.
Question
Which is a responsibility of the Project Assurance role?
Options
- AInform the Project Manager about the status of the project's products
- BDocument the Project Board's reporting needs
- CEnsure the Project Manager is aware of the need to use any existing corporate standards
- DInform corporate or programme management about the project's status
How the community answered
(33 responses)- A73% (24)
- B6% (2)
- C3% (1)
- D18% (6)