PR2F · Question #69
Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but the End Stage Report is not used to 'capture and maintain' information regarding issues and risks…
The correct answer is D. Give a summary of progress to date. See the full explanation below for the reasoning.
Question
Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but the End Stage Report is not used to 'capture and maintain' information regarding issues and risks. This would be in the respective Registers.)
Options
- ACapture and maintain information regarding issues and risks
- BDocument the project's acceptance criteria
- CEscalate a stage-level tolerance threat to the Project Board
- DGive a summary of progress to date
How the community answered
(33 responses)- A6% (2)
- B12% (4)
- C3% (1)
- D79% (26)