nerdexam
EXIN

PR2F · Question #69

Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but the End Stage Report is not used to 'capture and maintain' information regarding issues and risks…

The correct answer is D. Give a summary of progress to date. See the full explanation below for the reasoning.

Question

Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but the End Stage Report is not used to 'capture and maintain' information regarding issues and risks. This would be in the respective Registers.)

Options

  • ACapture and maintain information regarding issues and risks
  • BDocument the project's acceptance criteria
  • CEscalate a stage-level tolerance threat to the Project Board
  • DGive a summary of progress to date

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    12% (4)
  • C
    3% (1)
  • D
    79% (26)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice