PR2F · Question #62
When it is forecast that one or more tolerances are to be exceeded, what should happen first?
The correct answer is B. The appropriate level of management must refer the matter to the next higher level. See the full explanation below for the reasoning.
Question
When it is forecast that one or more tolerances are to be exceeded, what should happen first?
Options
- AThe next higher level of management will begin to execute management by exception
- BThe appropriate level of management must refer the matter to the next higher level
- CThe Project Plan will be replaced by a fallback plan
- DThe appropriate level of management will automatically produce and execute an Exception Plan
How the community answered
(29 responses)- A3% (1)
- B76% (22)
- C7% (2)
- D14% (4)