If any type of issue or risk (or aggregation of them) cannot be resolved within the tolerances set by the Project Board, which of the following products would first be sent to the Project Board to…
The correct answer is A. Exception Report. See the full explanation below for the reasoning.
Question
If any type of issue or risk (or aggregation of them) cannot be resolved within the tolerances set by the Project Board, which of the following products would first be sent to the Project Board to inform them of this deviation?
Options
- AException Report
- BEnd Stage Report
- CHighlight Report
- DUpdated Risk and Issue Registers
How the community answered
(27 responses)- A70% (19)
- B15% (4)
- C4% (1)
- D11% (3)
Community Discussion