The Product-based Planning technique is recommended for which plans?

The correct answer is C. All levels of plan. See the full explanation below for the reasoning.

Question

The Product-based Planning technique is recommended for which plans?

Options

  • AStage Plans only
  • BProject and Stage Plans only
  • CAll levels of plan
  • DAll levels of plan except the Exception Plan

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    73% (37)
  • D
    18% (9)